Project Completion Schedule

A Time for Every Season: Spring on the Prairie
Sargent Gallery
Lincoln Log Cabin State Historic Site
IHC Grant
  • Sept. 11                    design brief
  • Sept. 18                    draft narrative
  • Oct.  16                    grant deadline
  • Nov. 30                    grant notification
Research/ Label Writing
  • Sept. 4 - Oct. 1       theme develpment
  • Oct. 16                     preliminary outline
  • Oct. 28                     first draft
  • Nov. 13                   narrative walkthrough
  • Dec   4                    final label copy
Evaluation
  • Sept. 25 - Oct. 4     conduct interviews
  • Oct. 8 - 16              compile data
  • Feb. 12                    summative evaluation
Design
  • Oct. 16                     gallery model
  • Nov. 13                  complete floorplan
  • Dec. 4                      complete evaluations
Photography
  • Oct. 2                       web page design
  • Nov. 1- Nov. 17     artifact photography
  • Nov. 27 - Jan. 22    photo reproduction
Artifacts/ Graphics
  • Oct. 9                          preliminary selection
  • Oct. 23                        final selection
  • Nov. 17                       complete object data sheets
Graphics Production
  • Nov. 27 - Dec. 11  design information delivery system
  • Jan. 15 - 29            graphic panel layout
  • Jan. 29                    artwork to printer
Matting/ Framing
  • Jan. 15 - Feb. 5       matting/ framing
Exhibit Fabrication
  • Jan. 15 - Feb. 5       off site
  • Feb. 5 - 12              in gallery
Installation
  • Feb. 5 - 12              installation
Loans/ Usage permissions
  • Oct. 23 - Dec. 11
Opening
  • Feb. 16
   
   